cancel
Showing results for 
Search instead for 
Did you mean: 

Budget bottom up in CJ30

Former Member
0 Kudos

Hi experts,

I would like to ask if there is a possibility to revaluate values in cj30 in bottom up sequence. There is no bottom up check in budget profile maintenance screen (in planning profile such a check exists). Is the only possibility to use exit SAPLKBPB? Anyone try to do it? Thank you in advance.

Best regards

Paul Smuda

Edited by: Paul Smuda on Jan 4, 2012 8:05 PM

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member230675
Active Contributor
0 Kudos

There is no bottom up check in budget profile maintenance screen (in planning profile such a check exists).

Budget is always Top Down.

Please refer SAP Help for further details.