Base quantities in ECC routings and BOMs for APO PDSs

Former Member
0 Kudos

I'm trying to clarify the basic rules for how base quantities in BOMs and routing operations should be set for use in CIF to generate APO PDS.

- which base quantity appears in the APO PDS; is it the BOM base qty?

- do the BOM base quantitis and routing operation base quantities have to be the same?

Thanks for any information on this...

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

The unit of measure for operations in SAP ERP can deviate from the base unit of measure. You have to maintain a conversion factor in this case. During the transfer to SAP APO, the units of measure are converted to the header unit of measure.

Hope the information is useful

Regards,

Swetha