on 01-04-2012 4:24 PM
Hi experts,
We are developing a scenario using ABAP Proxy -> PI 7.3 -> JDBC.
When we try to run asynchronous interface, we get this error:
GET_BUSINESS_SYSTEM_ERROR An error occurred when determining the business system (COMMUNICATION_ERROR)
Communication error: Error when opening an RFC connection
The SLD configuration looks correct, with a Bussiness System related to the ECC Client that runs the ABAP code.
Any ideia about the origin of the problem?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have you tried SLDCHECK in ECC? Are your SLDAPICUST configuration correct?
Regards,
Prateek Raj Srivastava
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Error is related to the connection set up done between ECC and PI.
Test the connection using sldcheck.
HTH
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.