Hello Guys
I have a question in case of a Plan driven procurement with supplier collaboration. When a PO is created in MM is this first replicated to SRM and then to SRM SUS Client ? or directly to SRM SUS ?.
Second, how this PO is sent to this systems? Any configuration on this?
Third, can you please tell me how this connection is happen between the above in detail with configuration steps.
Thanks in Advance.
Hi Santhosh,
PO after creation in MM is directly sent to SUS.
PO from MM is sent as an IDOC or XML (if you use the ESOA architecture) via XI/PI to SUS.
Please have a look at configuration guide for 'Plan driven Procurement' from Service Marketplace.
Regards,
Nikhil