Why system is not giving maint/schedule as per Factory calender workdays

upinder_singh3
Explorer
0 Kudos

Hi PM Gurus

We have scenario of preventive maintenace with following set up

a) Factory Calender is maintained at work centre of Task list ,which has Sat ,Sunday and Public holidays as Non working days.

b) Maintenace Plan is set up for Scheduling parameters for scheduling indicator as (Time ) only.

Question : When we schedule maintence plan via IP10 ,this throws schuduling list for plan dates for Sat ,Sunday and Public holidays as well.

Pls provide your suggestions why we are getting this type of response or let us correct in case we have different understanding.Thanks

Upinder

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In IP02 you can also assign a separate factory calender .., You can change the Scheduling by Factory calender and then assign a factory calender to Plan ..check if this is helpful for ur case

regards

giri

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

you can solve the issue just select under scheduling parameters tab select the radio button Time-factory calander.

Regards,