on 01-03-2012 5:36 AM
hi all,
Issue is Open Quantity in SUS.
Service PO with service mAster Quantity 100 EA
Confirmation Service Master quantity 10 EA
SES created and Accepted with Quantity 8 EA
Confirmation status changed to Accepted by customer in SUS.
but Open Quantity in SUS showing 90 . It should be 92 (boz 2 Quantity Rejected)
how to change this.
regds
Rami
Could you reject partially in SES ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ramki,
if Supplier confirmed the Excess Quantity in SUS confirmation, which is getting creating SES in ECC. SO the User will check the Quantitis he actually Performed say in a perticular Month and change the Quantity in SES is Possible. In this case How to Get the Open Quantity correctly in SUS?.
regds
Ramireddy