Sequence of material line items in Project

Former Member
0 Kudos

Hi all,

I have transfered the BOM using CN33 in the project, the systems is configured such a way that after BOM upload the system creates PR automatically but, when the PR is created in the system the sequence of the line item material is not same as that of in BOM. How this has to be solved?

Best Regards,

Nitesh H Panchal

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

I am aslo using BAPI for uploading material component. What it is doing , it is creating the line item number in the sequence I am planning . Like if I planned material A first then it is creating line item number for that irrespective of its activity and WBS number.

Regards

Keshav

Former Member
0 Kudos

Hi,

I have the same requirment. I need to upload the materials in CJ20N.

Whci bapi you are using to upload the materials.

Please help.

Former Member
0 Kudos

Hello ,

As per my knowledge line item will appear according to sequence in activities. So line item of PR will come as per the materials are assigned to project CJ20N.

Regards

Keshav

Former Member
0 Kudos

Hi,

If i upload less than 10 materials then the line items are in sequence, but after uploading 50 or more materials the list of the material in the activites are in sequence but they differ from the line item number in PR.

Former Member
0 Kudos

Hi,

I have the same requirment. I need to upload the materials in CJ20N.

Whci bapi you are using to upload the materials.

Please help.