Hi Experts,

What is the program name to transfer PR from ECC system to SRM system.

And how purchase requisitions are transferred to SRM.

What will program name or how we can do the same ??

Thanks in advance.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Program name to transfer PR is BBP_EXTREQ_TRANSFER.

For all the configurations, please refer the 'Plan driven Procurement with Plant maintenance' config guide from service marketplace. (http://service.sap.com/srm-inst: SAP SRM -


SAP SRM Server 7.0---- Configuration Guides for SAP SRM 7.0 -


SAP SRM 7.0)

Regards,

Nikhil

Ramki
Active Contributor
0 Kudos

In addition to what Nikhil mentioned:

- PR transfer to SRM differs based on your SRM and ERP version.

You can also use SOA from ECC 6.0 EhP4 and SRM 7.0. SOA is mandatory if you want to use services PRs also.

You can download 'Plan driven procurement' from the link given by Nikhil .

(or https://websmp206.sap-ag.de/~sapidb/011000358700001156832009E)

See section 2.3.1 and determine how you want to configure.

Best regards,

Ramki

Answers (1)

Answers (1)

ricardo_cavedini
Employee
Employee
0 Kudos

Hello,

Have a look at note 1646982, which explains how to configure the external requirement scenario when transferring PRs via RFC.

Regards,