on 12-28-2011 5:14 AM
Dear All Experts,
I have configured the PS-Budget. While creating PO I am getting below error
Item 010 WBS element PCS-0012 budget exceeded
Message no. BP603
Diagnosis
Budget was exceeded by 100,00 INR in document item 010 WBS element PCS-0012 .
When I am looking in T.code CJ30 I can see for year 2011 Rs.30,000/- is available still getting error. The budget profile is also configured correctly. I am not checking budget at a Released level.
What step I am missing here to check ? or my approach is wrong. When I am looking at CJI5 I am not getting even a single line item posted on WBS still how I am getting error ?
Regards,
Shilpi Saxena.
Hi,
What is your PO Value? May be it becomes 30,100 after all considerable taxes !! Cross check this.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please check in CJ30 any budget is showing as distributable for that particular WBS Element.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Punith / krisap / Abdul.
Thank you all for your quick responses.
Punith : In CJ32 ONLY current budget column having values rest all is blank.
Krisap : I am creating for Rs 100.00 getting same error and then tested for Rs 1.00 getting same error for Rs 1.00 also.
Abdul : Thank you for explanation. In the said report S_ALR_87013558 I am seeing in Budget column
2011 : Rs 1,000
2012 : Rs 2,000
Overall values : Rs. 3,000
Anything else do I need to check ?
Regards,
Shilpi Saxena.
P.S. : My simple requirement is I have budget amount Rs 50,000 for total 5 years. Rs 10,000 each year. My year starts from 2011 to 2015 So in CJ30 I assigned Rs 10,000 every year. And I am getting error even for Single Rupee amount PO !
Edited by: CA Shilpi on Dec 28, 2011 10:19 AM
Edited by: CA Shilpi on Dec 28, 2011 10:21 AM
Hi,
1. As you said you are not having Availability control for budget releases, no need of checking CJ32. (assuming you are sure of this)
2. In the "Define Tolerance Limits" node, check whether you have maintained any % in the usage field.
3. In CJI5, removing the from & to date values in Expected Debit Date value range & cross check the report once again (another way is that to check the remaining column values in your S_ALR_87013558 report, apart from the original budget field. what is the available budget value showing for this particular WBSE?)
regards
Hi,
The following are the possible problems. pl check it will resolve ur issue
1. As you said budget is available in CJ30, check the availability control whether is at CJ30 level or CJ32 level, if it is at cj30 level no problem, if it is at Cj32 level pl check the released budget, release budget should have the cusion to take care of the PO if not enhance the relased budget.
2. check your tolorence limits, if it ok,
3. if above all is ok Please check the person resonsible in WBS element, if WBS element dosen't have person responsible also this error will occur, as in our tolorence limit setting "2" waring with email, while creating PO system check for the person responsible to alert him, if this is missing also this budget exceed problem will happen.
thanks
regards
kishore
Hey!
Just try to deactivate availablilty control, refresh project data base and activate the availabilty control and proceed with the PO
1. deactivate availabilty control: CJBW
2. Feresh data base: CJEN
3. Activate avialabilty control: CJBV
hope this will solve. even i have faced similar issue and the above said, worked.