The values are mismatch in S_ALR_87013558 budget report in many cases in one of my client. I have refreshed the project info database using CJEN & CJBN but in some case its not updating the values sp mismatch in budget report.
Kindly help on the same.
Thanks in advance.
KetanP
Hi Pradeep,
Actually, the client data volumn is very high so in many case i found this type of problem but it would be resolved by udpating project info database through CJEN and CJBN. I had checked the value category assignment via CJVC tcode where some of CEs are shown in yellow colour. As i understood i have to include all this cost element shown in yellow colour and then run CJEN & CJBN. Kinldy suggest me the step to include all this CEs with your valuable reply.
Thanks in adavance.
KetanP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi Ketan,
Please mention the exact mismatch you are facing in your budget report. Normaly CJEN and CJBN correct the project databace and to correct the PR PO commitment values please execute RKANBU01 correction report also. May be it can resolve your issue. And also you have to check your value categorries are in line.
regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
It is strange, S_ALR_87013558 takes the information from RPSCO table, could you check in this table if the information is or not correct?
Regards,
Sara
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.