Check at PR /PO level for budget exceeding in WBS project

Former Member
0 Kudos

Hi experts,

We have a requirement to put check for creation of PR and PO if budget exceeds for a particular WBS.

Kindly suggest the steps to configure the same in PS module.

thanks.

Accepted Solutions (0)

Answers (2)

Answers (2)

reena_ghadge
Participant
0 Kudos

Hi,

As explained by Sara, create budget profile and define the tolearnce limit here you can select ++ i.e tolerance limit for all activity groups and select the activity control action as error, warning or warning with mail to resp. person

former_member209919
Active Contributor
0 Kudos

Hi,

It is needed your controlling area has commitment management active. Then you have to make these settings :

SPRO --> PS -->Costs --> Budget

You have to create a budget profile, assign this to your project profile and then you can define tolerance limits for each operation ( warning and error messages),

I hope this can be useful, try to configure it and let us know if you need more information.

Regards,

Sara

Former Member
0 Kudos

Thanks Sara !