on 12-22-2011 11:16 AM
Dear Experts,
My Project Builder Screen is Like this I have only two tabs like Basic Data and Dates..In Basic Data Tab Page,I have these Options Project Type,Status [ System Status User Status],Responsibilties:Person responsible no:General Fields:Task rest of all i was put hidden... Now Im going like this way CJ20nproject definationWbs Overview.Here We have option like level,WBS,Wbs Description,Short ID,Project Type and Planning element etc.I want to display my user fied Task here..Can anybody please guided this issue...
By
Suma
Hi,
As Sara has suggested you need to check the settings maintained in the layout of WBS elements. Follow the path that Sara has mentioned. You have to change these settings to suit your requirement.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Suma,
Check your settings in SPRO --> PS --> Structures --> Operative structures --> WBS --> User interface settings --> Layout --> Define Layout of WBS detail screens. It is possible you have only activated these ¿?
regards,
Sara
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.