on 12-22-2011 10:38 AM
Dear Experts,
When I run payroll then the system displays error:
"Date specification 01 does not exist for 99 00 20 2012 01"
Help me, please!
Regards
Shaik Fareed
Hello
Error : Date specification 01 does not exist for 99 00 20 2012 01 means that this relates to Country 99, Modifier 00, Period paramter 20,Period 01 2012.
The above issue is due to inconsistent entries in table T549Q and T549S.
The error is due to T549S,the corresponding value is not maintained for the relevant period. Please maintain the value and retest it again.
Thanks and Kind Regards
Ramana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ramana and Mohan thanks for your reply..
In Payroll log am getting successful Personnel Numbers in that "Date specification 01 does not exist for 99 00 20 2012 01" is highlighted in Yellow colour.
Please guide me on the same.
Regards
Shaik
Edited by: Shaik Fareed Mohamed Ali on Dec 22, 2011 8:25 PM
Check IT0041 with Date type 01....and generation of Payroll periods..
If it is not there then run the report RPUCTP00
Mohan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.