Quality level maintenance

Former Member
0 Kudos

Hi,

We had initially three plants .For all those plants quality level is maintained for quality managed materials.

But these quality levels having no task list type, task list group and group counter.

I analyzed and found these are created automatically by system when inspection lot is created provided these (quality managed materials) materials should have dynamic rule defined for the inspection type.

Our problem is system is creating these quality levels not in the first instance i.e. it is creating the quality level while creating inspection lot for the second attempt.

I have following queries.

1) what is the use of quality level in inspection lot creation .

2) How the standard settings, if the quality level is created manually to trigger the quality level at first attempt?

3) As I have explained earlier we are creating new plant, if we need to upload cutover data for quality level?

If we do not what will happen? If we need to, then how?

Regards

Dina

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

u need to create the qualiy task list and assign DMR in quality plan.

secondly quality level used to analyize the lot acceptance and rejections.

Regards

Former Member
0 Kudos

Normally you do maintain the Quality level while creating a sampling scheme QDP1. You can create diffetent AQL levels for the same severity. While assigning the sampling scheme to the sampling scheme to sampling procedure you can select the AQL level required.

You can only change the inspection severity using a DMR but not the AQL level. You can change the AQL level by assigning a different sampling scheme.

Former Member
0 Kudos

If you are only concern about the quality levels as inspection severity. This is created in the sampling scheme and when you do the data migration for sampling scheme you can have this and This is getting triggered based on the DMR rule. The problem is when you do the data migration you can do it for Quality plan, DMR rule, Sampling plan and sampling scheme but you can not caryy over the current status .. The system will reset it to the 1st level based on the DMR used.

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi,

thanks to all for the valuable feedback.

krishnamurty_madduri
Contributor
0 Kudos

Hi,

Quality Level: Def: The quality level is a data record that the system automatically updates at the time of dynamic modification (at lot creation or when the usage decision is made), by checking the conditions for an inspection stage change and, if necessary, storing a new inspection stage for the next inspection.

The information in the quality level determines which inspection stage will be used for the sample determination of the next inspection lot. So, Quality Level works in conjunction with DMR.

1) what is the use of quality level in inspection lot creation .

Quality Level is only for changing Inspection Severity: Reduced-Notma-Tightened Inspections. Because DMR deals with skip lots/char, it keeps changing the Quality level, based on the settings you made in DMR. AQL depends on your industry requirements and is only useful for accepting/rejecting a lot.

2) How the standard settings, if the quality level is created manually to trigger the quality level at first attempt?

In Standard Settings, Quality Level initially is generally set to Normal Inspn. Based on DMR, it changes immediately upon UD. Quality Level can be created using the t-code QDL1, as above. You can change the next inspection severity manually in QDL2.

+3) As I have explained earlier we are creating new plant, if we need to upload cutover data for quality level?

If we do not what will happen? If we need to, then how?+

To start with, you don't have to define any Quality level. However, for DMR, you need to set-up the stages (severities) of inspection. That will ensure that Quality Levels are automatically updaed. Regards, KrishnaM

krishnamurty_madduri
Contributor
0 Kudos

Hi,

Quality Level: Def: The quality level is a data record that the system automatically updates at the time of dynamic modification (at lot creation or when the usage decision is made), by checking the conditions for an inspection stage change and, if necessary, storing a new inspection stage for the next inspection.

The information in the quality level determines which inspection stage will be used for the sample determination of the next inspection lot. So, Quality Level works in conjunction with DMR.

1) what is the use of quality level in inspection lot creation .

Quality Level is only for changing Inspection Severity: Reduced-Notma-Tightened Inspections. Because DMR deals with skip lots/char, it keeps changing the Quality level, based on the settings you made in DMR. AQL depends on your industry requirements and is only useful for accepting/rejecting a lot.

2) How the standard settings, if the quality level is created manually to trigger the quality level at first attempt?

In Standard Settings, Quality Level initially is generally set to Normal Inspn. Based on DMR, it changes immediately upon UD. Quality Level can be created using the t-code QDL1, as above. You can change the next inspection severity manually in QDL2.

+3) As I have explained earlier we are creating new plant, if we need to upload cutover data for quality level?

If we do not what will happen? If we need to, then how?+

To start with, you don't have to define any Quality level. However, for DMR, you need to set-up the stages (severities) of inspection. That will ensure that Quality Levels are automatically updaed. Regards, KrishnaM

krishnamurty_madduri
Contributor
0 Kudos

Hi,

1) what is the use of quality level in inspection lot creation .

Quality Level is only for changing Inspection Severity: Reduced-Notma-Tightened Inspections. Because DMR deals with skip lots/char, it comes in to picture here. AQL depends on your industry requirements and is only useful for accepting/rejecting a characteristic.

2) How the standard settings, if the quality level is created manually to trigger the quality level at first attempt?

In Standard Settings, Quality Level initially is generally set to Normal Inspn. However, it changes immediately upon UD - linking with DMR (as you know, in DMR, we define the next stage based on acceptance/rejection)

+3) As I have explained earlier we are creating new plant, if we need to upload cutover data for quality level?

If we do not what will happen? If we need to, then how?+

To start with, you don't have to define any Quality level. However, for DMR, you need to set-up the stages (severities) of inspection. Initially, if you do not set-up any quality level, it will be still OK.

Regards, KrishnaM