Hello gurus,
I have a forward sales order in which all the line items have 1-1.5 month future first date but one line item have 4-5 months future first date.
client question is on what basis this vary far date is getting calculated.
Please help.
Thanks
Hi,
This date is calculated either based on the ATP results or after carrying out delivery/transportation scheduling. Please check the stock situation of those materials. If transportation scheduling is active, check the lead time maintained in the determined route as well.
If you press "F1" in that field you will see how the system react on that field.
Best regards,
Rahal.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
the issue is with particular item, cleint is asking based on what calculation system is picking such a long date...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The material availability date is one of the criteria.
Please go to that sales order and that item schedule line and double click on the schedule line date.
here you can find three tabs SALES ,SHIPPING & Procurement.
Click on SHIPPING here you can find all the dates.
Hope this will guide you
Thanks
Dasaradha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.