on 12-21-2011 6:07 AM
When the PM ordr is created and released the order will take the budget from the WBS Element.
In Which report i can know the no.of PM orders which were released and the amount of budget it has taken.An the Budget avaialble in WBS element for the for the new PM orders to created and released.
Hi Prashanth,
The report is S_ALR_87013558 Commitments(Order Wise)
and for Balances you can check S_ALR_87013561
Hope it helps you.
Regards,
Yawar Khan