on 12-21-2011 5:03 AM
Hi Experts,
I am totally new to Plant Maintenance. My client has the below requirements.
1) Machine preventive maintenance schedule.(monthly/yearly)
2) Measuring instruments Calibration.
3) Maintenece schedules of PRT/Test equipment.
How to manage all the above requirements. Would be of great help if expalined the entire process flow in detail.
you can create various maintenance plans in IP41
create task lists either equipment task list or general task list based on your requirement
attach the task list in the maintenance plan
in the plan scheduling parameters, specify the sheduing frequency.
create a variant in se38 for the shedule program RISTRA20
in sm36 schedule a job so that the maintenance plans are scheduled thru a job and orders are created by the system
you may go thru F1 help of each box to know more about the individual fileds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.