I want to trigger an alarm for delayed activities without using workflow. Following is my scenario.
Network activities contains 10 days to complete the activities. I want to trigger an alarm on 8th day to person who is responsible for that activity. Is there any standard config in SAP PS or can we use notification.
Regards,
Gagan
Hi,
I think you may write some background job with proper logic which can trigger this alarm. And set frequency for this Back ground job.