hi all,

we are using PS + PP.

we creating bom against wbs element

MRP run on wbs element and process continues.

here i need to ask one question.

we have four sections in PS :

DESIGN, PROCUREMENT, PRODUCTION & DISPATCH.

BOM CREATED ON PRODUCTION WBS ELEMENT AND MRP RUN ON SAME WBS ELEMENT SO MY PROCUREMENT IS DON ON PRODUCTION WBS ELEMENT AND I COULDN'T GET CLEAR REPORT.

IS THERE ANY WAY THAT I WILL CREATE BOM ON PROCUREMENT WBS ELEMENT. PR / PO GETS CREATE AFTER MRP RUN ON PROCUREMENT BUT CONSUMPTION OF RAW MATERIALS WILL BE DONE AGAINST PRODUCTION ORDERS WHICH HAVING ASSIGNMENT OF PRODUCTION WBS ELEMENT. BUT IT SHOULD DONE BY AUTOMATIC PROCESS NO MANUAL PROCESS INVOLVE.

THANKS IN ADVANCE.

Edited by: SIng on Dec 20, 2011 2:32 AM

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member230675
Active Contributor
0 Kudos

Please use non-valuated project stock and also settle production order to production WBSE.

By using non-valuated project stock you can get actual cost of procurement on the procurement WBSE, where as on Production WBSE you will get only the transformation cost.

Please try with a new project and revert..

Former Member
0 Kudos

Try to settle the production order to WBS element.

Former Member
0 Kudos

hi,

i assign settlement rule with WBS.

i have complete the process and go for settlement of order in ko88.

i got error for allocation structure and settlement cost element.

please help me resolve the error