cancel
Showing results for 
Search instead for 
Did you mean: 

Stop Billing creation till PGI is Done

Former Member
0 Kudos

Dear Gurus,

I would request you to please help me in this configuration, we have a process where a STO is created and converted into Delivery (VL10B) and then we do Proforma Billing (VF01 with respect to Delivery) and after that we create Excise Invoice, in the current process we can create the Billing document as soon as we create a Delivery Document through VL10B without doing PGI, now the client wants that the Billing should not be allowed till the time the PGI is completed. please suggest how to configure this Requirement.

I tried making changes in the copy control VTFL of Delivery to Billing where i changed the Copying routine 009 to 003 at header level and 010 to 004 at Item Level but its giving an error that Item is not relevant for Billing while creating Billing Document.

Thanks in Advance

Ameet Singh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Please find the below links

Thanks

Dasaradha

Edited by: dasaradha ramireddy on Dec 15, 2011 3:16 PM

Edited by: dasaradha ramireddy on Dec 15, 2011 3:18 PM

Former Member
0 Kudos

Dear Dasaradha,

Thanks very much for your help.It solved my problem.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Amit1986,

--Go to T.Code VTLF & select your delivery document & billing document

--In item copying requirment assign the routine as 034(Item rel-With GI) & save it

--Now try to do the billing without doing PGI & check the output.system will not allow you to do the profroma billing without doing the PGI.

Let me know if your problem is solved

Regards

Pradeep

Lakshmipathi
Active Contributor
0 Kudos

In VTFL for item category, maintain routine 034 for "Copying requirements"

G. Lakshmipathi