on 12-15-2011 9:25 AM
Hello PS Gurus,
I am unable to explode BOM material ( M) in CN22 for one network activity (A). The same material M can be exploded in same network but different activity (B)
Please throw some light in this
MM
HI Menka,
While doing the BOM transfer have u maintained the reference point for the network activity(A) ?
Regards
Gaurav
Edited by: Gaurav206 on Dec 15, 2011 1:40 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
you can also transfer this BOM in activity without using Reference Point.
In CN33 you can enter Project Number and than click on select parameters (shift + F5) than in popup window you can select all items than run this. this will show all BOM material in first half and activity in project in second half.
Thanks
Sunil
Hi Menaka,
Please check activity type and check material should be attached in that network activity.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.