Value Difference in Actual Cost in Report S_ALR_87013533

Former Member
0 Kudos

Hi Experts,

This is regarding the Report S_ALR_87013533, System is showing different value at wbs level & its line item details level.

For Example:- Actual Value at WBS level is 6202556 in INR , when I am going to see the actual in line item details it is showing the total value 6503458. this is the value ofGL & Object Total in CO Area Currency in INR and in transaction Currency value is coming in two currency INR & EUR. But the value of WBS does not match with both of these value.

Please help in this matter..

Thanks in advance.

Ajay

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

There was a inconsistancy in in value catag. somany cost element was not asigned.

I have checked in IMG Project Syste > Cost > Val. catg.

Ajay