on 12-14-2011 7:36 PM
Hello
Is there a way if i can perform capacity levelling for labor which is shown in the work centers
please reply me , if my knowledge is accurate on that issue
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Make it as scheduling relevant in ECC itself...
I.e:If you want to consider labor in Capacity then you have to create a separate Work center under capacity category Labor. And in the capacity tab under processing tab use Labor * Operation quantity / Base quantity / Operation splits
Thanks and Regardss
Suresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Suresh
Thanks for the solution , I knew about this solution but my client wants to know the effect of other non human resources in Labor ( after running capacity leveling). I have mentioned that since the machine( SAP ) does not know the difference between a human and a machine , when we run capacity leveling on resource ( Filler ), it will not over load the labor resource. Since we are doing capacity leveling it will look for available buckets and if its able to level in that bucket then it wil give a message that it cannot level it in that period. We would also expect the 100% load on labor as well.