Hi All,
My scenario is,
1)I create maintenance strategy for preventive strategy plan.
2)assign that strategy to task list
3) create one maintenance plan
After some time i want to add one more package to both strategy as well as in task list.
can these changes reflect in my maintenance plan created before?
Regards,
Bhanu Pradeep
Hi Bhanu,
what you are saying is not possible for what all dates the documents are generated, but once the changes have been done then the orders generated after that can have the changes.
Hope it helps you.
Regards,
Yawar Khan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,Pradeep
unless you scheduled the concerned Maintenance plan you can add packages to strategy as well as tasklist.
Regards,
K.Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.