on 12-13-2011 11:35 PM
All,
Is there any standard transaction or BAPI/BADI to assign multiple materials viz 1000 plus to an Inspection plan.
Thanks
Anup
You have two option to upload mass materials to inspection plan.
Option1: Go to QP02 --> Material assignment screen. Here you can assign 14 materials at a time and do page down to assign next 14 materials. This is time consuming activity.
Option2: With help of techinical person develop LSMW/ BADI which call QP02 to update material assignment in inspection plan.
Please find few relavent descussion below, I hope it will help you take decisioon.