Control cycle mass creation with staging indicator 4

Former Member
0 Kudos

Hi All,

Is there any way to create control cycles in mass for staging indicator other than 3 - rel order parts?

Accepted Solutions (0)

Answers (1)

Answers (1)

csaba_szommer
Active Contributor
0 Kudos

You can define a generic control cycle for manual staging parts and it will be valid for parts w/o control cycle. Please read SAP online help:

http://help.sap.com/saphelp_erp60_sp/helpdata/en/c6/f841494afa11d182b90000e829fbfe/frameset.htm

...

For manual staging, you can define one control cycle per production supply area for all materials. This control cycle is then valid for all the materials in the production supply area, for which you have not defined an individual control cycle.

...

If you want other mass cration / change tool, you have to develop it on your own.

Edited by: Csaba Szommer on Dec 13, 2011 9:59 PM

Former Member
0 Kudos

Thanks for your reply. I would like to create control cycles for few hundreds of materials with one destination bin with manual staging indicator and also few thousands of materials with different destination bin with manual staging indicator, Is there any mass change program available once you create with staging indicator 3 from LPK4 or do i need to go with any custom programs, if so is there any standard BAPIs available, if not is BDC is the only option?