on 12-13-2011 4:29 PM
hi,
when i enter timesheet against an internal order which is linked to an item, the hours in the capacity planning view are coming one month behind the actual month in which the timesheets were entered. However, the financial view shows the values against the correct month. Ex:- when i enter my timesheets against any of the weeks in Dec, the cap. planning view shown it in November, but the financial view shows the values in December. We do not have any fiscal year variant defined. Following calendar year in PPM.
Can anyone suggest me of the possible reason for the same?
Hi,
Could you chech which information do you have in table RPM_FIDATA?
Regards,
Sara