Can suggest , in stardard SAP system can we configure the automatic determination of cost centre based on ordertype or main work centre?
Hi Thackerv,
when you work with an maintenance order, the order collects the cost, and that can be settled to a cost center using KO88.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dear,
You can have different settlement profiles defined in the system and assign them to different orders.
and at the same time you can have different allosation structure for different profiles.
Hope it helps you.
Regards,
Yawar Khan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
order and cost center are both cost objects. when you work with an maintenance order, the order collects the cost, which you settle to a cost center using KO88.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.