on 12-13-2011 6:57 AM
I am putting cost plan values in Tcode CJ40. But Project Planned cost are been updated in any repory .
if you are directly doing cost planning in cj40, then use t-code IMCCP3 - Transfer Plan to Project Budget . After then you can view the project Plan reports
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
"Hierarchical Cost planning in CJ40 not updating in CNS41" . Please check this post . It might help you. Next time please do some basic search before positng. If you are still facing the problem , then give the details you have tried.
Thanking you
Vengaiah Chowdary
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.