Hi,
I have the following Client Requirement.
When issuing the Goods against the Network/Activity, system should not allow the user to issue goods more than the Planned quantity in Project System.
E.g., Material Code : 1000001
Quantity in PS against activity 0015 is 10 Nos
Goods issue against the Activity is 12 Nos(the two nos were actually planned and received for some other activity)
Is it possible to Restrict the user from doing so.
Please suggest.
Thanks.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Use a Validation for not allowing a Material document having without Reservation for a particular Movement type.
with regards
M Umapathy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please use some user exit to put a validation.
Eg: User exit some thing like CMFU0002
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.