on 12-10-2011 6:53 PM
I am trying to create Resource with resource category H with planning version 000 in APO.
It is getting created with planning version independent.
Can you pl let me know how to create this resource with planning version 000?
Thanks,
Srini
Srini,
You have to assign any resource (H or otherwise) to the active model.if you want it to appear in a planning version.
/SAPAPO/RES01 ,Select your resource, 'resource change'. Select the resource, then F5. Select the resource, then Shift-F1. You can also use the icons if you don't want to use the hotkeys. Save.
Best Regards,
DB49