Billing Plan - Billing Rule set to Quarterly but error while executing

Former Member
0 Kudos

Hi All,

I have a typical problem, I have a Billing plan in which Billing rule - Quarterly is set. we have put Time period as 3 and Time Unit as Month. and i have Factory calender assigned to it in which i have maintained special rule for quarters like - From 09/30/2011 to 10/01/2011 for October billing. All assignment is perfect.

Everything is triggering but the problem is its skipping first quarter, combining the same with second quarter i ;e first line shows details of first 2quarters and then rest is working fine.

Can someone please let me know wats causing this.

Thanks in advance.......

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

resolved....

former_member184701
Active Contributor
0 Kudos

dear friend,

the problems seems to be in OVBS

which date you set as Baseline date?

did you set up Last on month and caledar ID there?

i also recommend to try with "Contract data" checkbox 'on' and 'off'

good luck!