on 12-08-2011 1:59 PM
Hello ,
We have in a WBS costs also for statistical CE which belongs to fixed assetes , This causes costs to be reflected in a report
S_ALR_87013533 . But these "double costs " ara also taken into consideration when I run the CNE1 for EV .
I want to exclude this specific CE from the Actual costs for the ACWP claculation .
How can I do that ?
Thank's
Gadi Rotem
Hi,
Goto SPRO - PROJECT SYSTEMS -- PROGRESS -- PROGRESS ANALYSIS -- PROGRESS COST ELEMENT ASSIGNMENT.
Give the controlling area.
Now you can see cost element group might be assigned to the EV cost element. Check that cost element group has your statistical cost elements. Remove from the group. Run the progress analysis.
Thanking you
Vengaiah Chowdary
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Thank's for the quick response , however :
I have CE with category 61 - Earned Value assigned to CE group PS_GENERAL .
This Group doesn't contain the statistic CE . category 90 .
still I get in CNE5 in Actual costs the costs also for the statistical
Do I have to add the statistical CE to the group or not ?
Thank's
Gadi
Hello ,
I have a specific CE ( 2800020 ) category 90 which is for the Fixed assets and we make settlement to from WBS to FXA .
We still see the costs of this CE in the WBS costs .
I have assigned CE category 61 ( 651100 ) to CE group ( PS-CO ) in customization . the CE group PS-CO does not
contain the statistic CE ( 2800020 ) .
Still after running CNE1 I get in CNE5 in Actual costs all the costs including the costs of statistical CE 2800020 .
What is wrong ??
Thank's
Gadi
Hello,
Please read the Sap Note:61414.
If a cost element categroy 90 is used for fixed assets. Then respective WBS should not be settled to the fixed asset. Because the fixed asset might be assign with same WBS as the CO object assignment. Which show the WBS with double costs.
To rectify that , we can reverse the settlement for that repective wbs.
please let me know if you any issues.
Thanking you
Vengaiah Chowdary
Hi,
Please check since how many months your are doing the settlement for the WBS. Now you have reverse the settlement for all the months.
Goto CJ88-- give the 1)wbs number --
2) settlement Period
3) fiscal year
Select Settlement in the menu bar. and in settlement we have REVERSE. Please repeat the step for all months you have done the settlement.
Thanking you
Vengaiah Chowdary
Hi
Thank's again for your reply . However we can't perform the reverse . There are too many WBS and for 5-6 months and
it' s a on going process when they settle to the asset .
I think I will open an OSS because I believe that for EV calculation SAP has to enable me to eliminate this statistical CE
from the calculation .
Thank's
Gadi
Please read SAP Help given in the IMG node of Maintain Assignment of Cost Element Group which will address your issue.
Please try one more time...
....create a new cost element group which contains the cost elements you required to be included in EV calculation and assign, also select the def. radio button.
... after running CNE1 and CNE5 I still get the same ACWP
Maintain Assignment of Cost Element Group will effect BCWS and BCWP only.
ACWP = Actual Cost,so it will be including statistical cost, Please try by changing your value category excluding and suppressing these statistical cost elements.
Please regenerate data base through CJEN and try.
Also try by creating a new project.
"ACWP = Actual Cost,so it will be including statistical cost, Please try by changing your value category excluding and suppressing these statistical cost elements."
Thank's Abdul for your input and clarification .
I have a specific value category - FXA for the statistical CE , However I don't understand how I can suppress this Value category when I run transaction CNE1 or CNE5 ? .
Or do you think that If I suppress the Value category in report S_ALR_87013524 will be sufficient for th EV calculation so
report will take ACWP without the FXA value category ?
Thank's
Gadi
Hello Abdul again ,
Thank's for your quick reply ,
I just want to make sure that I understand correctly , and I will use an example :
the ACWP in WBS 1 = 45M consists currently from 25 M actual ( real ) costs and statistical costs in Value vategory FXA = 20 M .
the BCWP = 20 M .
If I will manage, in a report S_ALR_87015124 , to suppress the Value category FXA then the "real" ACWP is only 25 M and
the CPI will be 20/25 = 0.8 ? while currently without supressing it is 20/45 = 0.44 ?
Am I right ?
Thank's in advance ,
Gadi Rotem
I doubt whether you can avoid Actual cost ( statistical actual cost) from the CPI calculation. Value Category only controls the display of Values in the report. since you have avoided these statistical cost elements from the cost element assignment it may work.
Please test and verify in your sand box / Dev. client.