on 12-08-2011 10:42 AM
Hello,
Can anyone pls tell me the logic to retrieve the Days since Sales Order creation excluding the holidays in Swedish factory calender.
Current logic which we have thought of is
(The first succesful output - Order creation date)
But the result should exclude the Swedish Factory calender holidays (our client is from Sweden)
Now we need to establish the logic of fitting the factory calender into this whole issue. As we have to provide the logic to our ABAP er .
Waiting to hear from u all.......
Regards,
Anirban
SD Consultant
Your message is somewhat unclear to me.
When creating a sales order, a "Required Delivery Date" is needed.
This date is checked against the unloading calendar of the customer. If the system finds the requested delivery date = a non-working day of the customer calendar, it issues a warning (No goods accepted on DD.MM.YYYY. The next possible date is: DD.MM.YYYY (Message no. V1019). There does not seem to be any possibility of changing this warning to an error in the standard system; only possibility would be to modify the standard code.
If I have misterpreted your thread, then apologies, and feel free to elaborate on the issue some more.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Anirban
Better u ask ur HR consultant only, Bcz he only create Factory Calender
If u give data to ur HR consultant they will define factory Calender according to ur requirement.
Satya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.