I am doing cost planning for my project using t-code CJ40.I am not getting the period tab for OVERALL Valus.
please suggest.
Regards
Prashant
Hi,
Check your planning profile in transaction OPSB. Check whether the "Total Values" check box is ticked.
Regards,
Gokul