on 12-07-2011 8:58 PM
Hi all,
How does one perform sales forecasting and planning in ECC? I understand there is SIS which will allow us to retrieve our sales actuals data, but how do we input forecasting and planning?
Thanks,
For MTS scenarios, he normal planning path is:
SOP (could be based on SIS) ---> Demand Management ---> MPS (optional) ---> MRP ---> Capacity Planning (optional).