on 12-07-2011 12:44 PM
Hi Friends
Need your Help!!
I need to change the Priority settings set for the support message in Solution Manager , If a user logs a support message in the ECC system (production) with any priority (low, medium, high, very high etc.) it should default to Incident in Solution manager.
From there the client wants to classify the Priority as per his requirement in Solution Manager.
The current settings are like below
For a Low Priority it is defaulting to Incident
For a Medium Priority it is defaulting to 1: Bug P1-2
For a High priority it is defaulting to 2: Bug P3-4
For a Very High Priority it is defaulting to 3: Bug P5-10
Really appreciate your help, many thanks.
Kind Regards,
Vattikonda.
Hi,
Sorry, but your question is not clear to me. Where exactly are you having a problem?
Rgds,
Sneha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
thank you for response.
It is the clients requirement to default the priority status to Incident if a support message is created from a managed system (ECC).
for e.g,
An user creates a support message in ECC production client giving the relevant input and he selects the priority as High, this created message should default to Incident in solution manager.
please see how the current settings are from my earlier at the bottom..
Kind Regards,
Sandeep.