MRP PR transfer to SRM using PI

Former Member
0 Kudos

We are facing issue to transfer MRP gererated PR to SRM in PDP scenario usng SAP PI

- Manually created PR can see in SXMB_MINI on ECC side but not seen on SRM Side

- MRP genereated PR not tranmitting at all tranmitted via PI

BADI ME_REQ_SOURCING_CUST in place.

Edited by: nniikkhhiill on Dec 8, 2011 10:00 AM

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Closed

Former Member
0 Kudos

Hi

Please go to the tcode /sappo/ppo2 for SRM 7.0 , it will give you the error .

Thanks,

Ashish

Former Member
0 Kudos

Hi

Please go to the tcode /sappo/ppo2 for SRM 7.0 , it will give you the error .

Thanks,

Ashish

former_member22425
Active Participant
0 Kudos

Hello,

BADI ME_REQ_SOURCING_CUST holds the logic for the PR transfer to SRM.

Kindly cross check the configuration for the same referring to the note 1263876 [SAP SRM: Configuration of Procure-to-Pay Scenario ].

Also check for the Account assignment category type in the PR generated from the MRP run in ERP. Not all the types are supported in SRM. Also the Purchasing group in the PR should match to the transfer logic you have configured in the BADI ME_REQ_SOURCING_CUST.

Also what is the status of the PR in PI. Check for the xml status. Is it successfully out from ERP system.

Best Regards,

Rahul

Former Member
0 Kudos

- MRP PR do not have any acct assignment

- Logic given in Badi "Purchase GRP XX" will transfer to SRM

- Even from ECC PR is not seen in outbound msg in SXMB_MONI