on 12-06-2011 12:52 PM
Hi All,
I have created SO with qty 10 on 06.12.2011
but in Schedule line it is confirming it only in 08.12.2011.
i have posted the stock manually by 561 mov. type.
why system in not confirming on today's date?
Schedule line category in CN-No MRP
Reg,
Amol
Check whether any safety stock is maintained in material master. Also the schedule line category should be CP