cancel
Showing results for 
Search instead for 
Did you mean: 

Schedule Agreement -

Former Member
0 Kudos

I have to update EDI messages only a schedule agreement is open . i should not consider schedule which is closed ...

where would be the status whether schedule agreement is open or closed

i checked vbak vbap vbuk.. i cant get to a solution

regards

Arunkumar,S

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear s.arunvinay,

You can easily get ths status of scheduling agreement by VBUK table.

Go to SE16N give the sales documnet number and execute. In that if you find VBUK-GBSTK =A the agreement is open. If VBUK-GBSTK = C the document is completed.

GBSTK is overall status of the document.

Please let me know if you have any further clarifications

Thanks&Regards

Raghu.k

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Arun,

Pass your agreement number into VBUK table for the field VBELN and fetch the status as above expert said.

Thank you,