on 12-05-2011 6:01 AM
Hi Friends,
Can anyone please let me know how can we prevent quotatios from getting considered in rescheduling program. Currently i have kept the availability check off for quotation but they are getting considered when we run the rescheduling program V_V2.
Please help.
Regards,
Wasim.
Check your schedule line cat getting determined for the Quotation.
Maintain either of them BN or BP.
Also check your quotation SD document categ. should be B.
If problem persists, refer SAP Notes
- 90230: Performance of rescheduling.
- 847986: Rescheduling performance
- 822884: Performance improvement for rescheduling
- 1138411: Performance of rescheduling
Regards
JP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.