Hi Gurus,
I am getting -ve floats in some of the activities in project scheduling. How can i stop this?
Suresh Patel
Hi,
Increase the finish date.
Thanking you
Vengaiah Chowdary
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Gurus,
>
> I am getting -ve floats in some of the activities in project scheduling. How can i stop this?
>
> Suresh Patel
why you want to stop negative float, it is a standard behavior, and same concept is there in Project management as well?