Dear All.

In Stability study if i have 10 Kg material i keep 5 Kg to 20 degree & 5 Kg for 30 degree so system create two physical sample for that i can assign two differnat inspection plan with 1 Month cycle & 2 Month cycle it is ok...

Now issue is i want to keep all quantity of 10 Kg for 20 degree but want 1 Month & 2 Month package for same material quantity please suggest how can we do this in SAP means for 1M pacakge 12 call & for 2 M package 6 call.

Thanks & regards.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi,

U need to maintain the two seperate strategy and in that what ever be the requirement set the calls as u said 12 calls in 1 mon and 6 calls in 2 mon cycle.

Assign it with inspection plan via QST04 .

Regards

Edited by: D GURU on Dec 2, 2011 8:39 AM

Former Member
0 Kudos

Dear Guru.

Tahnks for reply please suggest how can we assign two differant packages for single physical sample...

Regards.

dev123

Former Member
0 Kudos

Dear,

If i understand your requirement then You can use CWBQM for two inspection plan and maintain different packages for the same.

Regards,

Sandip

Former Member
0 Kudos

hi,

Via CWBQM,

U first create the inspection plan with two grp cntr for Physical SAmple and assigned Mateanace package and strategy with it.

Regards