Hi All,
We have changed the plan finish date of an item from 31.12.2011 to 31.12.2012. Corresponding Cproject project definition is in Released status. As a part of synchronization the dates on the Cproject project definition changes to 31.12.2012. But the dates are not copied to the lower hierarchy i.e. tasks. We have only tasks under PD.
System message is u2013 Can not update scheduling data
Reason u2013 As the Cproject is in Released status scheduling can not happen automatically. Scheduling should be carried out manually.
How to enable scheduling automatically when the Cproject project is Released. Business do not want manual scheduling of Cproject project.
Regards,
Gaurav
Will try and follow the procedure mentioned .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Gaurav,
There's no standard way to activate the automatic scheduling once the project has been released.
You will have to enhance standard class CL_PPM_SCHEDULING / method GET_SCHEDULING_FORCE and force the parameter rv_scheduling_force to abap_true.
Regards,
Matthias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
you can try the BAdi from 1095100. Normally it is used to DE-activate automatic scheduling. But it is worth a try, if you can also ACTIVATE it
Cheers
Thorsten
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
6 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.