on 12-01-2011 7:08 AM
Gurus,
We have a scenario where we need to select the production version (out of say 2 production versions) with least lead time during the optimization run. Please note that the production version with least lead time is not the default production version which is used in planned order while planning run.
Is it possible to select the production version with least lead time through optimization run?
Thanks in advance!
Snigdho
Hi,
Yes, it is possible. Since optimizer is the cost based planning, it can be controlled through the costs maintained at the PDS/PPM and the delay costs in product master.
If you set minimum cost (single level variable cost will be considered by optimizer) for the least lead time production version i.e., PDS/PPM, the system will consider priority to this.
Regards,
Manimaran M.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks a lot for your help.
I will rephrase my problem:
I am working on a single planned order where I would like the system to select the correct production version with least lead time (and that has to be done at the time of optimzation as the planning run is done based on the default production version). We have only two versions, the first one has the highest lead time.
I have also maintained mode priorities with the second version having priority A (with least cost maintained in the profile). Now since I am having only one order I caanot enter order priority for delay costs.
In this scenario how the system can pick up the second production version so as to schedule the order with minimal lead time?
Thanks again
Snigdho
Hi,
I hope you use PPDS optimizer. Make sure that single level variable cost is maintained less for the least lead time PDS than the other one.
Also please check your optimization profile - Order creation tab. The setting should NOT be 'No order creation'. If it is, then it will not delete and recreate the order, instead, it will try to adjust the existing order.
Regards,
Manimaran M.
Hi,
If you are using PPDS Optimizer- it works as per following logic
1. PPDS Optimizer can't change source of supply so if you have 2 PDSs - it wont move order from one PDS (resource) to another
2. If you want PPDS Optimizer to select reosurce/production version based on lead time, you need to maintain aleternate Sequence in Routing/Receipy which will become anotehr mode in PDS
Let me know if you have any other query.
Vipul
Manimaran,
Could you please let me know for such case which optimizer profile would you use? And even if I maintain the cost in PDS_MAINT (in R/3) and CIF the data, which cost will this hit in Optimizer run? I believe this cost should not be reflected in setup cost or mode cost. And in case of delay cost we enter the cost based on priority, but in case of multiple production versions I am not entering the cost in delay, rather entering the same in the PDS only. A little more insight might help me...
Thanks
Snigdho
That answer is right. the PP/DS Optimizer does not change the production version (PDS or PPM in APO to be correct) of an order.
If you want the PP/DS optimizer to decide on alternative resources you need to have alternative modes in the activity of the operation of the order. To get alternative modes you need alternativ sequences in the ERP routing. The PP/DS optimzer cannot change components (requirements) if you have alternative BOMs in you production versions.
The SNP Optimizer is able to do that. The SNP Optimizer will select the production version (PDS or PPM) with the lowest cost. If you maintain the cost in relation with your lead time it will work as desired if not other costs disturb the result.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.