on 12-01-2011 2:51 AM
Dear experts,
Is there any report in PS where i can see list of projects has actual balance and commitment balance?
Note: I want to see only the balance of actual cost ( which is not settled) and commitment balance (Open PO, PR etc..)
Regard
Vetrivelan
You can use report S_ALR_87013542 which allows drill down functionality (the actual column leads to CJI3 and the commitments column leads to CJI5).
Regards,
Ammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There is no report for Balance unsettled cost against WBS in PS. Report for Balance Commitments will be available in S_ALR_87013542.
with regards
M Umapathy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
For commitment- CJI5
actual - CJI3 with correct layout as per you requirement.
also try S_ALR_87013558 report & go to line item report for detail actuals(& you have to change the layout accordingly) & commitment.
hope this would help you...
regards,
SL
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try tcode gr55 and vairant Z6P2.
Thanking you
Vengaiah Chowdary
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.