PS report for Actual and commitment Balance

Former Member
0 Kudos

Dear experts,

Is there any report in PS where i can see list of projects has actual balance and commitment balance?

Note: I want to see only the balance of actual cost ( which is not settled) and commitment balance (Open PO, PR etc..)

Regard

Vetrivelan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You can use report S_ALR_87013542 which allows drill down functionality (the actual column leads to CJI3 and the commitments column leads to CJI5).

Regards,

Ammar

Answers (3)

Answers (3)

Former Member
0 Kudos

There is no report for Balance unsettled cost against WBS in PS. Report for Balance Commitments will be available in S_ALR_87013542.

with regards

M Umapathy

Former Member
0 Kudos

Hi,

For commitment- CJI5

actual - CJI3 with correct layout as per you requirement.

also try S_ALR_87013558 report & go to line item report for detail actuals(& you have to change the layout accordingly) & commitment.

hope this would help you...

regards,

SL

former_member388328
Active Contributor
0 Kudos

Hi,

Try tcode gr55 and vairant Z6P2.

Thanking you

Vengaiah Chowdary