project was set to TECO

Former Member
0 Kudos

Good Morning PS gurus,

Please advise in which transaction , we can see which date a project was set to TECO?

Thanks

MM

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

use t-code SQVI, join the tables PRPS and JCDS. It will show the details of wbs wise & status wise dates.

with regards

M Umapathy

Former Member
0 Kudos

Many Thanks to Uma & Ammar,

We donu2019t have any transactions to see the projectu2019s when the status was changed ( I mean time & date).

Thanks in advance.

MM

Former Member
0 Kudos

There is no standard report for status wise & date wise reports for Projects in PS.

Develope a Z report.

with regards

M Umapathy

Former Member
0 Kudos

Thanks for ur help.

Former Member
0 Kudos

Hi,

On cj20n once select WBS/proj defn. ->click on system status 'i ' icon then -> Extars->change document->all-> double click on system status you want to see detail.

regards,

SL

Former Member
0 Kudos

Hi Sam,

Thanks for the information. Can we get the same for multiple projects in any transctaion.

Thanks once again

MM

Former Member
0 Kudos

Use TCode CN60 to view change documents for multiple projects. You will get additional line items for every change and therefore will need to filter your results based on your requirements.

Please also ensure whether change document has been activated for the respective project profile (for further details search the forum on change documents).

Regards,

Ammar