on 11-28-2011 9:12 AM
Without Cost center, is it possible to schedule and release inspection lot 14 for instrument calibration.
I tried without CC, but inspection lot has not triggered, if i give cost center either in work center or equipment data, then every thing is happening.
Please advice...
Yes,
Bcoz PM order is an Cost object whcih needs some cost center, without this order will not released and thus ur lot not triggered.
Enter Cost Centre .
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Without relevant work center & cost center ( costing object) its not possible to have lot for calibration.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.