on 11-27-2011 4:34 PM
Hi Experts
I have a service PO with GR based IV active,
Entered SER/GR and IR for partial quantity.
Subsequently i have entered second Invoice directly (with out SER/GR).
But the commitment amount has not been reduced with second invoice.
How to ensure that the commitment amount is updated with invoice amounts?
Thanks and warm regards
ramSiva
Try the following:
1) Please run report RKANBU01 for the incorrect projects in question. This will update any incorrect commitments. Further details can be found in the note above.
2) After running the reports above, please run report RKACOR04 as this will correct any problems between the line item tables and the total record tables.
3) After running the above reports, please run transaction CJEN for all the projects as this is very important so that the database gets updated.
4) Finally run report CJBN which rebuilds the availability control for each project.
Also review the following notes:
1491430 - Incorrect Commitments for Service Items
1492317 - Incorrect commitments after posting service entry sheet
Regards,
Ammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.