cancel
Showing results for 
Search instead for 
Did you mean: 

Background job cancelled

Former Member
0 Kudos

Hi,,

every day background jobs

Job Ln Job CreatedB

SAP_REORG_UPDATERECORDS SAP*

SAP_WP_CACHE_RELOAD_FULL SAP*

cancelled.

and job log is ---

Job started

Step 001 started (program RSM13002, variant SAP&001, user ID OSEBASIS)

Reorganization of update date not allowed in batch

Job cancelled

Job started

Step 001 started (program RWP_RUNTIME_CACHE_RELOAD, variant SAP&RELOAD_ALL, user ID OSEBASIS)

No component system chosen

Job cancelled after system exception ERROR_MESSAGE

Please help me out.

and tell me what is the purpose of theses jobs.

Regards,

Vivek

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Please check the following SAP Notes:

Note 1034532 - Changes for standard jobs

Note 16083 - Standard jobs, reorganization jobs

Hope this helps.

Regards,

Varun

Former Member
0 Kudos

as mention in sap note ---1034532

Solution

The following changes are delivered with the Support Packages specified below:

1. The following job definitions are deleted:

SAP_REORG_UPDATERECORDS (program RSM13002)

SAP_WP_CACHE_RELOAD_FULL (program RWP_RUNTIME_CACHE_RELOAD)

and this note is delivered on SP basis 14 and current sp of my system is 14

then why this issuse comes.

REgards,

Vivek

sunny_pahuja2
Active Contributor
0 Kudos

Hi,

If you check SAP note 16083, it clearly states that SAP_REORG_UPDATERECORDS and SAP_WP_CACHE_RELOAD_FULL should be deleted from the schedule as it no more required. So, you should delete this job from scheduled jobs.

Thanks

Sunny

Former Member
0 Kudos

thanks to all.

Regards,

vivek

Former Member
0 Kudos

got ans